92 | | * Next week's plan: Complete building the spec/build files and work on the linkercmds compatible for the RPi4b |
| 92 | * Next week's plan: Complete building the spec/build files and work on the linkercmds compatible for the RPi4b |
| 93 | * June 22: Coding period second meeting |
| 94 | * Previous week's work: completed the spec/build files for the minimal RPi4b. Started testing the A72 qemu build on the the raspberry pi and making changes to the relevant part of the kernel |
| 95 | * blockers: Using GDB is new to me so it's taking some time to understand, although using gdb is fun. |
| 96 | * Next week work: I'll be still working on the kernel using the gdb and based on that , i'll be doing the relevant work needed. I'll be writing about all the things i've learned in the upcoming blog. |